The Latta Bridge, located along Jasper Avenue, northeast of 91 Street and southwest of 90 Street, will be replaced.

Project Update - December 2020

The project team is currently working on the preliminary design which is anticipated to be completed and shared in spring 2021.

Stakeholder engagement will begin in early 2021, prior to the completion of preliminary design.

About the Project

Latta Bridge was originally constructed in 1911 and currently serves as an arterial roadway with 4 lanes of traffic. Latta Bridge is located along Jasper Avenue, northeast of 91 Street and southwest of 90 Street.

The bridge crosses Latta Ravine, the site of a maintenance access trail, which provides further access to Dawson Park and the river valley.

A Condition Assessment, Load Evaluation and Management Strategy Report was completed in December 2019 and recommended full replacement of the bridge.

Project Timeline

concept phase

Spring 2022

Anticipated construction

Winter 2021/2022

Detailed design

Spring 2021

Preliminary design

For More Information

Mitchell Schutta

Title Engineering Project Manager
Email lattakinnaird@edmonton.ca